Ticker

6/recent/ticker-posts

Risk Analysis and Prioritization

 

After risks have been identified and enumerated, the next step is risk analysis. Through

risk analysis, we transform the risks that were identified as decision-making information. In turn, each risk is considered and a judgment made about the probability and the seriousness of the risk. For each risk, the team must do the following:

®    Assess the probability of a loss occurring. Some risks are very likely to occur. Others are very unlikely. Establish and utilize a scale that reflects the perceived likelihood of a risk, such as: very improbable, improbable, probable, or frequent.

®    Assess the impact of the loss if the loss were to occur. Delineate the consequences of the risk, and estimate the impact of the risk on the project and the product such as 1=negligible, 2=marginal, 3=critical, or 4=catastrophic.

 

The analyzed risks are organized into a risk table as below:


 


After the risks have been organized into a risk table, the team prioritizes the risks by ranking them. The team sorts the list so that the high probability, high impact risks percolate to the top of the table and the low-probability, low impact risks drop to the bottom.  If numerical values were given for probability and impact, the risk exposure can be calculated. Risk exposure is calculated as follows:

Risk Exposure (RE) = P × C

where P = probability of occurrence for risk and C is the impact of the loss to the product should the risk occur.

After the risks are prioritized, the team, led by the project manager, defines a cut offline so that only the risks above the line are given further attention.

Post a Comment

0 Comments